Itereration start date has changed.
The last iteration for us started on Jun 1 and ended on Jun 22. All the stories were moved to Done. Today, I logged in and found that all of the stories in that iteration have moved back to Current. The current iteration now lists the start date as Jun 8 and going until Jun 29. This is messing up our project cycle. How can we move the start date of the last iteration back to Jun1?
3
people have this problem
I have this problem, too!
Tell me when someone solves it.
The more people who report this problem, the more it gets noticed.
The more people who report this problem, the more it gets noticed.
The company marked this problem solved.
-
Inappropriate?Hi, Tracker calculates the first iteration's start date based on the week of the very first accepted story. To force your first iteration to start a week earlier, open the first done story, and change it's accepted date to be the week of Jun 1. You may need to reload the project afterward, but the iterations should shift back a week. Please let us know if you have any problems.
1 person says
this solves the problem
-
Inappropriate?Thanks, that fixes the issue.
Loading Profile...



EMPLOYEE