Changing my current sprints start date...help needed
My team is trying to change the itteration dates setup for our project. Tracker shows our sprint as 16 Feb - 1 March. Our team however is working on a sprint 9 Feb - 23 Feb...can I reset Piv Track so it aligns with our dates?
3
people have this question
I have this question, too!
Tell me when someone answers.
The more people who ask this question, the more it gets noticed.
The more people who ask this question, the more it gets noticed.
-
Inappropriate?Hi, Tracker calculates iterations automatically, based on project settings, and the earliest story accepted date. To "shift" your iterations forward by one week, you can open the Done panel, and change the accepted dates of the stories in the first iteration (Iteration 1) to the week of Feb 9. You may need to reload the project afterwards.
Please let us know if this does not solve the issue.
thanks
dan